ECOfluid Systems Inc. is pleased to announce it has been awarded an equipment supply contract to deliver a membrane bioreactor (MBR) wastewater treatment package plant that will service the community of Pinecrest Estates located approximately 20km South of Whistler, BC.

The existing wastewater treatment plant was commissioned in 1979 and subsequently upgraded in 1987. In December 2015, the Squamish-Lillooet Regional District (SLRD) board certified that the SLRD would assume ownership of the Pinecrest Water and Wastewater systems as of January 1, 2016. Since assuming ownership the SLRD was successful in receiving grant funding to replace the existing extended aeration plant. ECOfluid is proud to partner with TRUE Consulting and Acres Enterprises Ltd. on this project.

Start-up and commissioning of the new system is expected to be completed in March, 2018.